By The Utah Asphalt Pavement Association
Western Rock
Project location: US89 and SR143; Asphalt Rehab near Panguitch
US-89; MP 115-124, 131-141 and SR-143; MP 45-51 asphalt highway rehabilitation for UDOT Region 4. We were the general contractor for the production and delivery of 52,000 tons of SMA and 42,600 tons of HMA. We also supervised the in-place cold asphalt recycling of 123,600 square yards of roadway, 212,300 square yards of milled surface, roadway excavation and preparation for a center turn lane in the town of Hatch, and guardrail, signs and striping improvements throughout the project.